Wednesday, 14 June 2017
Friday, 9 June 2017
Week 3
5 - 9 June
I will try to track the progress weekly. Our plan was released for construction on 23 May 2017. That makes this the third week of construction.The slab was planned this week but it has been raining. Waffle pod and other materials have been delivered. Waiting for the weather to be kind!
Friday 9 June 2017
Rain has stopped and site has been ready for concrete.
Tuesday, 6 June 2017
Slab !!!!!!
Saturday, 3 June 2017
Slab
We visited the site with kids over the weekend.
Nothing much happened in last week.
Our site supervisor has advised us that slab will be poured till the end of next week. We can not wait to see some action now ..
Demolition
Demolition Starts.. |
Old House is Gone .. |
Silt Fenc |
Fences |
Subscribe to:
Posts (Atom)
-
Welcome to my Journey .....!!!!!!!!! We decided to knock down and rebuild as we love the area and neighbourhood. Its has been a lon...