I will try to track the progress weekly. Our plan was released for construction on 23 May 2017. That makes this the third week of construction.

The slab was planned this week but it has been raining. Waffle pod and other materials have been delivered. Waiting for the weather to be kind!






Friday 9 June 2017

Rain has stopped and site has been ready for concrete.





No comments:

Post a Comment

Framing

Frames are done !!